The last of the old wooden piles in the Inner Harbour have all but gone from the Lyttelton landscape.
Jetty 5 was demolished before Christmas, and Jetty 4 will be finished by the end of the week.
Senior Project Manager Razvan Secareanu says there are twenty-five piles left to go.
“It’s been a success, especially with removing all the Mediterranean fanworm from the Inner Harbour on Jetties 4, 5 and 6,” says Razvan.
A few piles along the southwest corner of Jetty 6 will also be removed.
Nine steel piles will be driven along the eastern side of Jetty 4 to create a physical separation and mark the previous location of the jetty.
“It will be a visual guidance for our Marine Team and the tug pilots. Each pile will be painted yellow and have a light on top, and it should be finished by the end of March.”
LPC corporate office
Waterfront House
37-39 Gladstone Quay
Lyttelton 8082
New Zealand
Postal address
Private Bag 501
Lyttelton 8841
New Zealand
Phone: (+64 3) 328 8198
Email: office@lpc.co.nz
For more contact details click here.
© Lyttelton Port Company Limited 2020.
Your use of this website is governed by or Terms of Use and Privacy Policy